Agrana; Austria, Pischelsdorf

bioethanoltanks
1 piece mash-mix-tank ø3,6m, H=8m, material:P235GH
2 piece caustic-storage-tank ø3,5m, H=6,6m, material: P265GH
1 piece sulfuric-acid-tank ø3,0m, H=4,0m, material: P235GH
1 piece fuseloil-decantig-centrifuges ø3,3m, H=2,0m,
            material: 1.4301

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

AKR- Modulgas GesmbH; Austria

biogasplant - BV Hollern (500kW)
biogasplant BV Lichtenwörth (500kW)


piping of natural gas- and transportpipes, heatingsystem and equipment assembling (material: 1.4301, 1.4571; PE; P235TR1)

Assembling

------------------------------------------------------------------------------------------------------------

 

Andritz AG; Voreppe, France

muddrying plant:
40 to steel construction, piping and insolation

Engineering / Manufacturing / Assembling


Andritz AG; Sloakia, Ljubljana

muddrying plant:
42 to steel construction

Engineering / Manufacturing / Assembling

Andritz AG; Austria, Eferding

muddrying plant:
80 to steel construction
         assembling of pipes and equipment

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

ATG; Austria

laying of district heating pipes DN 20 - DN 250
~ 30 km pipepath/year

district heating Schladming
~ 10 km pipepath DN20-DN200 laying of pipe and long-distance line

district heating Oberpullendorf
~ 5 km pipepath DN150 laying of pipe and long-distance line within insolation and long-distance leading system, boiler house installation

district heating Oberwart
~ 5 km pipepath DN150 and DN200 laying of pipe and long-distance line within insolation and long-distance leading system, boiler house installation, pipeing of transferstation and heatexchanger

district heating Aspang
~ 8 km pipepath DN20-DN150 laying of pipe and long-distance line within insolation and long-distance leading system, boiler house installation

district heating Laßnitzhöhe
~ 9 km pipepath DN20 - DN150 laying of pipe and long-distance line within insolation and long-distance leading system, boiler house installation

district heating Bad Kleinkirchheim
~ 15 km pipepath Dn20-DN150 laying of pipe and long-distance line within insolation and long-distance leading system, boiler house installation, pipeing of transferstation

Assembling

------------------------------------------------------------------------------------------------------------

 

Austrian Energy & Environment; Austria, Arnoldstein

waste incineration plant:
detailengineering, material supplying, manufacturing and assembling of

200 t steel construction, handrails, stages and landings
  50 t pipeline bridge constructions
  21 t exhaused gas pipes DN500-DN1000 (stainless steel)
110 t activated coke absorber
  40 t SCR plant
  30 t mechanical haulage systems
  35 t piping DN15 to DN300 carbon- and stainless steel
120 t equipment assembling

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

AVE; Austria, Regau

exhaust gas pipes:
manufacturing and assaembling of pipes and supports (stainless steel)
~150 to steelstrukture
1000 m  piping DN100 - DN1400

Engineering / Manufacturing / Assembling


reconstruction gas reducing station

Assembling

------------------------------------------------------------------------------------------------------------
 

AVN; Austria, Dürnrohr

waste incineration plant:
steel construction and insolation

110 t       steel structure
1.600 m2 insolation
25 t          mounting constructions

Engineering / Manufacturing / Assembling

annual audit Block I und II inclusive Engineering and coordination

Engineering / Assembling

pipeing and tanks
Assembling

reconstruction electrostatic filter plant

Assembling

catalytic converter retrofit
Assembling

------------------------------------------------------------------------------------------------------------
   

Babcock Borsig Power Environment GmbH; Turkey, Iskenderun

2500 to electrostatic filter

Engineering / Manufacturing

------------------------------------------------------------------------------------------------------------
 

Begas; Austria, Burgenland

1200 lfm. steam duct DN350
Static, pipe engineering, steel structure and insolation

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
    Caliqua; Austria, Wels

WAV II turbine pipeing for waste incineration plant:
~ 4,6 km DN25 - DN600 live steam pipes to cooling water pipes and equipment assembling
material: 1.4301, S235JR, P235GHTC1, -TC2, 16Mo3

Assembling

Caliqua; Switzerland

4800 m hot water pipe DN350 inclusive reating and assembling of supportingconcept

Engineering / Assembling

------------------------------------------------------------------------------------------------------------
 

CTU; Austria, Güssing

biomassplant
46 to steel construction inclusive detailengineering assembling of piping, supporting concept and insolation

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Ebner; Austria, Ebensee

mother liquor plant
430 to steel construction(dimension: H 26 m, B 20 m, L 50 m)

Engineering / Manufacturing / Assembling

mother liquor tank
ø 6120 mm, H = 7500 mm, material: 1.4571

Manufacturing / Assembling

Ebner; Germany, Töging

vapor piping
~ 100 m pipes DN200 - DN600, material: 1.4539, 1.4541

Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

Energie AG; Austria, Riedersbach

high pressure wastewater sludge pipes DN150 PN100

Engineering / Assembling

------------------------------------------------------------------------------------------------------------
 

EVN AG; Austria, Pöchlarn

natural gas high pressure pipe DN200 PN70

Assembling

EVN AG; Austria, Dürnrohr

annual audit Kraftwerk Dürnrohr

Assembling

redevelopment electrostatic filter (fild 2 and 3)

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

E-Werk Reutte; Austria, Vils-Reutte

ca. 15 km high pressure gas pipe DN200
ca. 15 km pipe laying (material: PE DA 225 bis DA 25)
150x  houseconection


Engineering / Assembling

------------------------------------------------------------------------------------------------------------
   

Fernwärme Wien bay houseplants; Austria, Wien

warn water transferstations (until 400 kW)
heating transferstations
primary transferstations (until 2 x 1400 kW)

(about 30 to 40 stations per year)

Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

Fisia Babcock; Germany, Mannheim, Oberhausen

1000 to electrostatic filter Mannheim
250   to electrostatic filter Oberhausen
             
Engineering / Manufacturing

------------------------------------------------------------------------------------------------------------
 

Gerstl; Austria, Wels

connection bridge Fachhochschule - BFI
20x2,5x3,5m (LxBxH)
additional about 27to steel construction (for soundproofing and elevators)

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

GSD Gesellschaft für Stadt- und Dorferneuerung; Austria, Wien

elevator retrofit in buildings (city vienna)

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
   

Kanzler Verfahrenstechnik; Tunis

seewater-desalination
150 to steel construction

Engineering

------------------------------------------------------------------------------------------------------------
 

Lafarge Perlmooser AG; Austria, Retznei

annual audit
Assembling

dissolvent plant
about 20 to steel structure
about 1000 m pipeing DN15-DN100
(material 1.4301, 1.4571, S235JR)

Manufacturing / Assembling

clinker cooler assembling
about 15 to substructure
assembling of clinker cooler (weight about 150 to)

Manufacturing / Assembling

Lafarge Perlmooser AG; Austria, Mannersdorf

annual audit
Assembling

assembling of hot gas duct
ø 2500 mm, Material 1.4301

Assembling

cement tank
~ 10 to  ø 4200 mm, H=16 m

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Lenzing Lyocell GmbH & Co KG; Austria, Heiligenkreuz

Linie 2
10x pressure vessel ø 1000 - 6000mm (material: 1.4571)

Engineering / Manufacturing / Assembling

8x bursting vessel (ø900mm, L=2800mm)

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

MCE Energietechnik; England

biodieselfuel plant Teeside 1
precast of the plant in containerdesign (about 40 containers = about 120 to) inclusive piping (about 2900m) and equipment assembling

Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Oestu Stettin; Austria, Wien

terrorprotection
3 pieces height limiting to protect the building of the UNO

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Rote Mühle Deutschland; Iran

air preheater rotor
50 to steel construction, material: COR-TEN B (S355J2G1W)
     
Manufacturing

------------------------------------------------------------------------------------------------------------
 

Rudolf; Austria Purkersdorf

redevelopment of a historical platformroof
~ 100 to steel construction disassembling; redevelopment and partial substitution with new parts; assembling

Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Salzburg AG; Austria, Bruck-Kaprun Gasteiner Tal

gas-medium pressure duct

Assembling


Salzburg AG; Austria, Trumersee


1800 m gaspipe DN300 PN 70
installed under way in the Trummer sea

Assembling

------------------------------------------------------------------------------------------------------------
 

Tiroler Ferngas GmbH; Austria, Tirol

natural gas supply
medium pressure pipe (material carbon steel)
low pressure pipe (material: PP)

Assembling

------------------------------------------------------------------------------------------------------------

 

voestalpine Donawitz; Austria, Donawitz

high crane rail - free storage rail 3+4
120 to steel construction (assembling in two weeks)

Engineering / Manufacturing / Assembling

EG3 - blast furnace air-supply
steel construction, pipes (DN15 to DN1400) and a lot of dwelling work

Engineering / Manufacturing / Assembling


2 Stk. pressure vessel (waterconcept 20K)
ø 3500mm, L=8m, thickness to 15mm, material: P265GH

Engineering / Manufacturing / Assembling

pipeing BG5000 (waterconcept 20K)
(DN25 - DN1400, Material: P235TR1, S355J2G3)

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------

 

VAI Voest Alpine Industrieanlagenbau GmbH; Austria, Donawitz

84 to        piping mediapackage of panoven incl. subsurface piping
23 to        plant piping (powerplant reconstruction)
8000 m    pipes DN15 to DN400
                 (material: carbon- and stainless steel)

Engineering / Manufacturing / Assembling

VAI Voest Alpine Industrieanlagenbau GmbH; Germany, Dillingen

piping extrusion casting plant Line3 / Line 4
20.000 m   pipes and equipment

Engineering / Assembling

VAI Voest Alpine Industrieanlagenbau GmbH; Slowika

2 piece cooler tank - VDK
ø 4500mm, height 20m, 58 to/piece, material: 16Mo3 and P265GH

Engineering / Manufacturing

VAI Voest Alpine Industrieanlagenbau GmbH; Austria

125 to cooling package (sheet metall 3mm Mo3, length 12m)
  65 to steel construction and stairtower

Manufacturing


VAI Voest Alpine Industrieanlagenbau GmbH; Russia/Alchevsk
Brasil/Rio de Janeiro

flareheads
~ 130 to manufacturing and creation of assembling drawings
               material: P265GH, 1.4828

Manufacturing

------------------------------------------------------------------------------------------------------------
   

VA-Tech Hydro; Schwizerland, Cleuson-Dixence

5 to support construction
        for pressurepipe ø 2688mm, material: S355J2G3, S355JR

Manufacturing

------------------------------------------------------------------------------------------------------------
 

Waagner Biro Brückenbau AG; Äthiopia

Panelbridge:
200 to steel construction

Manufacturing


Waagner Biro Brückenbau AG; Austria, Wien

truck-turn-bridge (Columbus-Center Vienna)
35 to steel construction

Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------
 

Weinkellerei Wegenstein; Austria

pallet-delivery-bridge
45 to steel construction incl. piping of filling machine

Engineering / Manufacturing / Assembling

------------------------------------------------------------------------------------------------------------

 

Wiener Linien; Austria, Wien

subwaystation: U1-Station, Taubstummengasse, Praterstern
steel construction for elevators, facing- and interior work

Engineering / Manufacturing / Assembling

subwaystation: "U1-Leopoldau"
complete interior work:
12.000 m² facade facing made of sound-protection-panelen,
                  Emailpanel, Alupanel
     720 m² glas-steel-facade
     300 to  steel consupstruction

Engineering / Manufacturing / Assembling